Lukas Richter opened a discussion in Operate, about finance: I deleted every vague line from my statements of work last month. For a year I'd been writing 'plus anything else we discussed' and then working the extra week for free. 5 replies so far. Mei A. Ng says: Automatic billing clauses don't survive a client's finance team, and they really won't in Germany. The change order has to exist before the work, not the invoice after it. 4 other replies add further detail below.

2
Finance

Stopped eating scope creep on my own dime. What's the first concrete move?

Lukas Richtergbeya team

I deleted every vague line from my statements of work last month. For a year I'd been writing 'plus anything else we discussed' and then working the extra week for free. My fixed-price ad audits were finishing at about half the rate I planned, and the unpaid overrun was roughly a third of my billable quarter. I'm done with it, but I want the first move right, not the whole system. I'm a one-man shop in Munich, and every hour I lose here is an hour I'm not putting into the second offer.

5 replies

  • 0
    Georgie A. Stirlinggbeya team

    The uncomfortable bit: your clause isn't the problem, your rate is. I doubled mine and scope creep stopped mattering nearly as much. Half your fix is a price rise, not a document.

  • 0
    Hugo A. Hennessygbeya team

    A change order. One page. The moment something falls outside scope, I send it before I start the work. Client signs or we pause. Added maybe 20% to my last three jobs.

  • 0
    Thabo Bothagbeya team

    Easy fix. Put a line in the SOW saying out-of-scope work bills automatically at your standard rate. Then you never have the awkward conversation again.

  • 0
    Mei A. Nggbeya team

    Automatic billing clauses don't survive a client's finance team, and they really won't in Germany. The change order has to exist before the work, not the invoice after it. Thabo, that one gets disputed every time.

  • 0
    Naledi Nkosigbeya team

    Charge discovery separately. It's the filter.

Highlights from this conversation

Points raised

  • “Automatic billing clauses don't survive a client's finance team, and they really won't in Germany. The change order has to exist before the work, not the invoice after it. Thabo, that one gets disputed every time.” Mei A. Ng
  • “The uncomfortable bit: your clause isn't the problem, your rate is. I doubled mine and scope creep stopped mattering nearly as much. Half your fix is a price rise, not a document.” Georgie A. Stirling
  • “A change order. One page. The moment something falls outside scope, I send it before I start the work. Client signs or we pause. Added maybe 20% to my last three jobs.” Hugo A. Hennessy
  • “Easy fix. Put a line in the SOW saying out-of-scope work bills automatically at your standard rate. Then you never have the awkward conversation again.” Thabo Botha

Explore this topic

This discussion sits in Operate, which holds 96 conversations. Running the business without chaos: CRM, automation, workflows, finance, delegation and productivity.

Related discussions

Go deeper

Reference pages that cover the practical side of this topic.

Browse every public discussion